1 |
BAB-E-PESHAWAR FLYOVER |
|
Completed by 85%. |
1772.492 |
2 |
PESHAWAR UPLIFT PROGRAM |
27 schemes.
Progress
04 schemes completed by 100%
03 schemes completed by 80%
04 schemes completed by 50 – 60%
14 schemes completed by 30 - 40 %
02 schemes contract being awarded
Additional funds of Rs.713.935 (M) required.
|
27 schemes in progress |
2980.262 |
3 |
BEAUTIFICATION OF PESHAWAR FROM ZAKORI BRIDGE TO SURAI PUL. |
Progress 60% (Feb 2015)
|
60% |
103.533 |
4 |
BEAUTIFICATION AND UPLIFT OF MUNICIPAL AREAS ON G.T ROAD FROM PABBI TO JHANGIRA |
Design approved. Cost estimation in progress.
|
Cost estimation in progress. |
400.00 |
5 |
FEASIBILITY OF GENERAL BUS STAND IN PESHAWAR |
MOU for design & build signed with NLC. Presentation to Honorable C.M for final approval of design in 2nd week of December, 2015.
|
pending |
100.00 |
6 |
PROVISION OF LED ROAD LIGHTS FROM ZAKORI BRIDGE TO ADMINISTRATIVE BOUNDARY |
|
Tenders opening |
139.00 |
7 |
CONSTRUCTION OF PRE-FABRICATED ELEVATED U-TURNS/DEDICATED U-TURNS IN PESHAWAR |
Discussed with NLC/ consultant. Because of widening of Jamrud Road, no space will be available.
|
no space will be available. |
1000.00 |
8 |
NORTHERN SECTION OF RING ROAD (MISSING LINK) PESHAWAR FROM PAJJAGI ROAD TO WARSAK ROAD |
Land for Warsak road intersection is being acquired.
Contracts awarded.
Pajjagi Road Flyover (10 months)
Road Work (12 months)
iii. Budni Nullah Bridge (06 months)
|
Contracts awarded |
6989.00 |
9 |
UP-GRADATION OF RADIAL ROADS LEADING TO RING ROAD. |
11 schemes.
Progress
06 schemes completed by 90%
01 scheme completed by 5%.
04 schemes, Bids received. Contract being awarded..
|
in Progress |
400.00 |
10 |
NORTHERN SECTION OF RING ROAD FROM WARSAK ROAD TO NASIR BAGH ROAD INCLUDING LAND COST |
PC-I for land acquisition approved @ Rs.2827.00 (M) .
Process in hand.
|
PC-I for land acquisition approved |
8500.00 |
11 |
CONSTRUCTION OF SHINGLED SERVICE ROAD FOR RING ROAD FROM HAYATABAD TO CHARSADDA ROAD |
Summary forwarded to Honorable C.M for revision of cost /change of scope @ Rs.1871.5 (M).
|
Summary forwarded to CM |
200 |
12 |
UP-LIFT OF REGI MODEL TOWN (RMT) INCLUDING PROVISION OF UTILITIES AND OTHER INFRASTRUCTURES (PHASE-I) |
Progress
Sui gas and electrification work in progress.
Additional funds of Rs.800.00 million over & above the CFY ADP 2015-16 provision are required.
|
Sui gas and electrification work in progress |
1000.00 |
13 |
SAFE CITY HAYATABAD PROJECT. |
Revised PC-I has been approved by PDWP conditionally. The requisite action is being taken by PDA prior to award of contracts.
|
Revised PC-I has been approved |
400 |
14 |
CONSTRUCTION OF HAYATABAD DETOUR INCLUDING SERVICE ROAD AND BRIDGE. |
Progress
Road Work 70%
Bridge Work 50%
Work partially suspended owing status quo issued by the Court.
Summary moved for land compensation (Phase-II) to the Honorable C.M
|
70% |
489.272 |
15 |
AMALGAMATION OF JAMRUD ROAD WITH SERVICE ROAD FROM TAMBWANO MORH TO HAYATABAD. |
Progress Payment of Rs.25.00 (M) made to PESCO for shifting of HT/LT lines.
Consultant appointed. Work on design and estimation in progress.
|
Ongoing |
NaN |