On-goingProjects

S# Project Achivement Project Cost (M)
1 Development of site at the confluence of M-1 & Ring Road. 75% 56.540
2 Widening & Improvement of existing G.T Road from Zakori Bridge to Surai Pul bridge Peshawar (section-1) and improvement of existing Jamrud Road from Shama Chowk to Administrative Boundary. 98 481.949
  Description:Completed. Except asphaltic concrete on a portion measuring 450 meter due to Status quo obtained by Pakistan Railways.  
3 Construction of Hayatabad detour including service road (one side), toll plaza and 3-No. bridges Ph-I (02-Km). 70% 489.272
  Description:Road work …. 75% Bridge work ….60%. Status quo obtained by locals.  
4 Rehabilitation/improvement of Pajjagi road from Bacha Khan Chowk to Bacha Khan Markaz Bashir Abad 60% 66.129
5 Rehabilitation/impt: of Abbaseen Floor Mill Dalazak Road to link road Arbab Niaz Stadium, Peshawar 80% 35.913
6 Group of Roads 40%
  Description:a. Rehab: & Impt: of Police Chowki Road b. Ijaz Abad road upto Sir Syed School Chowk c. Afridi Ghari Ring Road to Khyber Eye Foundation d. Farid Abad to Ijaz Abad and side drain upto UC-II, Peshawar e. Ishrat Cinema road to Sir Syed School chowk  
7 Impt: of Shami Road from Bacha Khan Chowk to Federal Lodges 35% 48.156
8 Rehab: & Impt: of Afghan Colony canal to Faqir Abad police station via Ashrafia colony, Peshawar 65% 59.76
9 Rehab: & Impt: of G.T Road to Kabul River canal via Govt. college, Peshawar 50% 57.029
10 PC-II for Construction of Elevated U-turns on Jamrud Road 0% 5.000
  Description:Matter has been taken up with NLC as suggested in minutes of the DDWP.  
11 PC-II for beautification of Hayatabad Consultant appointed. 5.400
12 PC-II for construction of service roads along Ring Road award of contract for consultancy is under process 24.00
  Description:Combined evaluated report was approved by DCSC in its meeting held on 04.11.2015. The award of contract for consultancy is under process.  
13 Construction of retaining wall and road along Narai Khawar at Taj Abad 50% 67.002
14 Outfall drain from Jameel chowk to Afridi Ghari Contract being awarded 59.59
  Description:PC-I approved. Contract being awarded.  
15 Construction of Janazgah and Playground in PK-5 4.500
16 Rehabilitation of drain and construction of footpath along main road at Phase-V Hayatabad 50% 67.002
17 Construction of Roads 10% 18.99
  Description:a. Road Opposite Akbar Town, Peshawar. b. Gur Mandi Road and construction of drain Hashtnagri, Peshawar c. Nasir Bagh Road to Madina street end Murad Abad, Peshawar  
18 Development of Green Belt along Railway line Jamrud Road from Phase-V Entry Hayatabad to Administrative Boundary Karkhano Market, Peshawar Work order stopped 52.37
  Description:Work order issued work stopped due to status quo obtained by Pakistan Railways.  
19 Shifting of PESCO HT & LT Lines from Tambowano Mor to PDA Nursery Phase-III Chowk Left & Righ both sides on Jamrud Road 0% 32.436
20 Remodeling of Gora Qabristan check post Ongoing 26.000
21 Rehabilitation/impt: of inter college road upto Charsadda road to Peshawar 43% 26.436
  Description:a. Rehabilitation/impt: of inter college road upto Charsadda road to Peshawar b. Rehabilitation/impt: of Wazir Colony Road, Peshawar  
22 Sardar Ahmad Jan Colony Street. No. 1 from Ring Road to Afghan Colony Road, Peshawar Contract being awarded to NLC. 16.841
  Description:a. Sardar Ahmad Jan Colony Street. No. 1 from Ring Road to Afghan Colony Road, Peshawar b. Road from Ring Road to Jehangir Hujra, Peshawar c. Faisal Colony to G.T Road, Peshawar d. Gulshan Colony to G.T Road, Peshawar  
23 Rehabilitation/Impt: of Road from Gul Abad Chowk to Faisal Colony Chowk, Peshawar 80% 23.006
24 Up-gradation of Kabul River Canal Road Via Afridi Ghari to Ring Road 65% 20.882
25 UP-gradation of Kabul River Canal Road Via Radio Pakistan Transmission Line to Ring Road. 85% 49.082
26 Rehabilitation / Improvement of Dalazak Road from Bacha Khan Chowk to K.R.C Yousaf Abad Peshawar. 15% 59.955
27 G.T Road Via City Town to Mortor way Peshawar 85% 21.325
28 Rehabilitation / Improvement of Dalazak Road from Yousaf Abad (KRC) to Ring Road Peshawar. 5% 59.599
29 Ring Road to Joe Sheikh Via Latif Abad Peshawar Tender received. Contract being awarded 17.93
30 Up-Gradation of Road Bacha Khan colony to Ring road Peshawar. Tender received. Contract being awarded 22.799
31 Up-Gradation of Road Sardar Ahamd Jan Colony to Mohmand CNG Ring Road. Tender received. Contract being awarded 14.727
32 Up-Gradation of Road Ring Road via Jehangirabad No.2 along with joe Sheikh canal to Garhi Baloch. Tender received. Contract being awarded 59.358
33 Bab-e-Peshawar Flyover 77% 1772.492
34 Peshawar Uplift Program Progress 2980.262
35 Provision of LED Road Lights from Zakori Bridge to Administrative Boundary PC-I approved. Tenders invited. 139.00
36 Northern section of Ring Road (Missing Link) Peshawar from Pajjagi Road to Warsak Road Ongoing 6989.00
  Description:Land for Warsak road intersection is being acquired.  
37 Up-gradation of radial roads leading to Ring Road. 90% 400
  Description:11 schemes. Progress 06 schemes completed by 90% 01 scheme completed by 5%. 04 schemes, NIT invited. (16.11.2015). Details are placed at Annexure-II.  
38 Northern Section of Ring Road from Warsak Road to Nasir Bagh Road including Land Cost. PC-I for land acquisition approved 8500
  Description:PC-I for land acquisition approved @ Rs.2827.00 (M). Process in hand.  
39 Beautification of Peshawar from Zakori Bridge to Surai Pul. 60% 103.533
40 Beautification and Uplift of Municipal areas on G.T Road from Pabbi to Jhangira Cost estimation in progress. 400
  Description:Design approved. Cost estimation in progress.  
41 Up-lift of Regi Model Town (RMT) including provision of utilities and other infrastructures (Phase-I) work in progress 1000.00
  Description:Progress Sui gas and electrification work in progress. Additional funds of Rs.800.00 million over & above the CFY ADP 2015-16 provision are required.  
42 Construction of Hayatabad detour including service road and bridge. 70% 489.272
  Description:Progress Road Work 70% Bridge Work 50% Work partially suspended owing status quo issued by the Court. Summary moved for land compensation (Phase-II) to the Honorable C.M  
43 Amalgamation of Jamrud Road with service road from Tambwano Morh to Hayatabad. Ongoing NaN
  Description:Progress Payment of Rs.25.00 (M) made to PESCO for shifting of HT/LT lines. Consultant appointed. Work on design and estimation in progress.  