S# Project Achivement Project Cost (M)
1 Bab-e-Peshawar Flyover Completed by 85%. 1772.492
2 Peshawar Uplift Program 27 schemes in progress 2980.262
  Description:27 schemes. Progress 04 schemes completed by 100% 03 schemes completed by 80% 04 schemes completed by 50 – 60% 14 schemes completed by 30 - 40 % 02 schemes contract being awarded Additional funds of Rs.713.935 (M) required.  
3 Beautification of Peshawar from Zakori Bridge to Surai Pul. 60% 103.533
  Description:Progress 60% (Feb 2015)  
4 Beautification and Uplift of Municipal areas on G.T Road from Pabbi to Jhangira Cost estimation in progress. 400.00
  Description:Design approved. Cost estimation in progress.  
5 Feasibility of General Bus Stand in Peshawar pending 100.00
  Description:MOU for design & build signed with NLC. Presentation to Honorable C.M for final approval of design in 2nd week of December, 2015.  
6 Provision of LED Road Lights from Zakori Bridge to Administrative Boundary Tenders opening 139.00
7 Construction of pre-fabricated Elevated U-turns/dedicated U-turns in Peshawar no space will be available. 1000.00
  Description:Discussed with NLC/ consultant. Because of widening of Jamrud Road, no space will be available.  
8 Northern section of Ring Road (Missing Link) Peshawar from Pajjagi Road to Warsak Road Contracts awarded 6989.00
  Description:Land for Warsak road intersection is being acquired. Contracts awarded. Pajjagi Road Flyover (10 months) Road Work (12 months) iii. Budni Nullah Bridge (06 months)  
9 Up-gradation of radial roads leading to Ring Road. in Progress 400.00
  Description:11 schemes. Progress 06 schemes completed by 90% 01 scheme completed by 5%. 04 schemes, Bids received. Contract being awarded..  
10 Northern Section of Ring Road from Warsak Road to Nasir Bagh Road including Land Cost PC-I for land acquisition approved 8500.00
  Description:PC-I for land acquisition approved @ Rs.2827.00 (M) . Process in hand.  
11 Construction of Shingled service road for Ring Road from Hayatabad to Charsadda Road Summary forwarded to CM 200
  Description:Summary forwarded to Honorable C.M for revision of cost /change of scope @ Rs.1871.5 (M).  
12 Up-lift of Regi Model Town (RMT) including provision of utilities and other infrastructures (Phase-I) Sui gas and electrification work in progress 1000.00
  Description:Progress Sui gas and electrification work in progress. Additional funds of Rs.800.00 million over & above the CFY ADP 2015-16 provision are required.  
13 Safe City Hayatabad Project. Revised PC-I has been approved 400
  Description:Revised PC-I has been approved by PDWP conditionally. The requisite action is being taken by PDA prior to award of contracts.  
14 Construction of Hayatabad detour including service road and bridge. 70% 489.272
  Description:Progress Road Work 70% Bridge Work 50% Work partially suspended owing status quo issued by the Court. Summary moved for land compensation (Phase-II) to the Honorable C.M  
15 Amalgamation of Jamrud Road with service road from Tambwano Morh to Hayatabad. Ongoing NaN
  Description:Progress Payment of Rs.25.00 (M) made to PESCO for shifting of HT/LT lines. Consultant appointed. Work on design and estimation in progress.  